2017-05-05 to 2019-10, Entrance to Leibnizstraße (Juridicum building site)

May 05, 2017 to Oct 01, 2019

The law car park has been closed since Whitsun 2017 and the building site has started to be set up. This means additional measures - on top of simply putting up a fence and signs:

  • Widening and tarmacking Schwarzer Weg for access to the building site, as well as changing the access to the sports forum
  • Moving the sports forum entrance barrier
  • Preparing provisional access for deliveries via Schwarzer Weg to the entrance to LS 4
  • Preparing a space for bike stands
  • Setting up a building site container and the preparatory measures associated with this

 

Full size

See a photo documentation of this building site


Thank you for your understanding.
Your Facility Management

Add to your iCal calendar

zurück

2017-07-05 to 2017-11, Heinrich-Hecht-Platz (excavation)

Jul 05, 2017 to Nov 30, 2017

Excavation at Heinrich-Hecht-Platz

The civil engineering works for relocating modular buildings are well advances. The modular buildings will be errected as from Octobre 2017. 

  • September 4 to 30 Construction of foundation
  • Octobre 2 to November Errection of modular buildings
  • from mid-November Move of research group

Full size

Add to your iCal calendar

zurück

2017-07-14 to 2017-11, Ludewig-Meyn-Straße 8 (Geography building site)

Jul 14, 2017 to Nov 18, 2017

Preparations for the new building on Ludewig-Meyn-Straße 8 are ongoing and are expected to continue until the middle of November.

The following measures are specifically planned in the vicinity of LMS 8:

  • Putting in the supporting walls from (very loud, lots of vibrations)
  • Excavation (medium noise level)
  • Explosive ordnance detection at foundation level (no noise)
  • Redirecting the media lines (low noise level)

 

Full size

See video and photo documentation of this building site


Thank you for your understanding.
Your Facility Management

Add to your iCal calendar

zurück

2017-09-18 to 2017-12-22 Leibnizstraße 6, 8, 10, 11 (conversion elevator system)

Sep 18, 2017 to Dec 22, 2017

In the coming weeks, the elevator systems within the faculty blocks an the Centre for Physics will be technically modernized. (Leibnizstraße = LS)

The following works will take place:

  • LS 6        2017-10-30 – 2017-11-17 (waterside elevator)
  • LS 8        2017-09-18 – 2017-10-06 (street side elevator)
  • LS 10      2017-12-04 – 2017-12-22 (street side elevator)
  • LS 11      Sept 18 to Oct 6 + Oct 30 to Nov 17 (freight and passenger elevator)