2017-07-05 to 2017-11, Heinrich-Hecht-Platz (excavation)

Jul 05, 2017 to Nov 30, 2017

Excavation at Heinrich-Hecht-Platz

The civil engineering works for relocating modular buildings are well advances. The modular buildings will be errected as from Octobre 2017. 

  • September 4 to 30 Construction of foundation
  • Octobre 2 to November Errection of modular buildings
  • from mid-November Move of research group

Full size

Add to your iCal calendar

zurück

2017-10-23 to 2017-10-27 Restricted traffic to Heinrich-Hecht-Platz (delivery of modular buildings)

Oct 23, 2017 09:00 AM to Oct 27, 2017 05:00 PM

The modular buildings will be delivered and set up on Heinrich-Hecht-Platz from Monday 23 October to Friday 27 October. This will result in temporary restrictions for through-traffic during the whole day along the entrance from Westring into the road by Heinrich-Hecht-Platz, as well as around the building site. Please expect brief delays.

 

full size

Add to your iCal calendar